Caltrans Logo

Reconstruct I-5 / SR-74 Interchange

Description: In San Juan Capistrano, on Route 74 from Route 5 to east of the city limit. Reconstruct the Route 74 and Route 5 interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City San Juan Capistrano
Zip Code 92675
 
Senate District
36
Assembly District 73
Congressional District 49
 
Caltrans District
12
 
 
County/State Route Orange 74
Postmile Begin/End 0 0.2
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      2479  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)      0  
Peak Period Time Savings (minutes)      197411  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of San Juan Capistrano Nasser Abbaszadeh 949-443-6398   NAbbaszadeh@sanjuancapistrano.org
Design (PS&E) Phase
Department of Transportation Nooshin Yoosefi (949)724-2131   Nooshin _Yoosefi@dot.ca.gov
Right of Way Phase
Department of Transportation Nooshin Yoosefi (949)724-2131   Nooshin _Yoosefi@dot.ca.gov
Construction Phase
Department of Transportation Nooshin Yoosefi (949)724-2131   Nooshin _Yoosefi@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $2,814 $2,814
CMIA
$15,926 $8,183 $24,109
Non-bond Funding
State/Federal*
$62,014 $-19,234 $42,780
Local**
$8,274 $-766 $7,508
Non Budgeted ETC
$0 $0 $0
 
Total**** $86,214 $-9,003 $77,211

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,700 $0 $1,700 $668
Design(PS&E)
$7,373 $-210 $7,163 $7,170
Right of Way
$31,753 $0 $31,753 $31,658
Construction
$45,388 $-8,793 $36,595 $38,367
 
Total* $86,214 $-9,003 $77,211 $77,864

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/27/2005 

06/01/2009 
01/01/2006 

06/01/2009 
01/01/2006 

06/01/2009 
100  06/30/2006 

06/01/2009 
-6 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

06/01/2012 
06/01/2009 

04/23/2012 
05/01/2009 

04/23/2012 
100  05/01/2009 

04/23/2012 


Begin Right of Way Phase

End Right of Way Phase
03/11/2011 

05/15/2012 
04/01/2010 

02/04/2020 
02/01/2010 

11/26/2016 
100  02/01/2010 

11/26/2016 


Begin Construction Phase

End Construction Phase
10/19/2012 

02/02/2015 
08/22/2012 

11/22/2016 
06/30/2012 

11/01/2016 
75  06/30/2012 

11/01/2016 


Begin Closeout Phase

End Closeout Phase
02/02/2015 

02/01/2017 
12/01/2016 

02/04/2020 
11/01/2016 

12/31/2018 
100  11/01/2016 

02/04/2020 


-13 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 2479
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 0
Peak Period Time Savings (minutes) 197411

Bond Funding Cost
Adopted:
$15,926,000
Current Approved:
$24,109,000
Actual Expenditures:
$23,686,000

 

Status as of December 31, 2023.